GarverUSA.com:

Construction Portfolio

City of Huntsville
Street Resurfacing

Client: City of Huntsville
Location: Huntsville, Alabama
Project Cost: $3.79 million

Project
Garver is providing construction engineering and inspection, materials sampling and testing, and contract administration services for Phase I and Phase II of the City of Huntsville's American Recovery and Reinvestment Act of 2009 (ARRA) stimulus-funded project. Phase I and Phase II include the planing, resurfacing, and traffic striping of 12 city streets and nearly 18.7 miles.

Garver's specialized services include performing erosion prevention and sediment control inspections, traffic control inspections and serving as traffic control supervisor, and field surveying.

Construction Phase Services Provided
  • Bidding/negotiation assistance
  • Contract administration
  • Owner, contractor, and public coordination
  • Construction materials testing coordination
  • Construction documentation
  • On-site construction observation
  • Review contractor's schedule and pay requests
  • Change order reviews
  • Final inspection
  • Project closeout documentation
Contact
Scott Leach
226-534-5512
SCLeach@GarverUSA.com